Four city schools will over-admit for September 2027 because Darwin Green Academy will not be ready. Applications open on 11 September and close on 31 October.

Parents in Cambridge can apply for a Year 7 place from Thursday 11 September, and families in the north west of the city are applying for a school that will not exist.

Cambridgeshire County Council has confirmed that four city secondary schools will take extra pupils in September 2027 rather than open Darwin Green Academy early or in temporary buildings. The decision is set out in a letter to Year 5 parents from Sarah Callaghan, the council’s Service Director for Education, dated 1 July 2026.

The council forecasts about 700 children seeking a Year 7 place across the Chesterton, North Cambridge Academy and Impington catchments in September 2027. Those three schools between them offer 570 places. Impington Village College sits in Impington, about three miles north of the city boundary; the other two are in Cambridge.

Which schools will take extra pupils

The council calls this Option B. Four schools have agreed to over-admit, giving at least 95 extra Year 7 places:

  • The Netherhall School, up to 30 extra pupils
  • St Bede’s Inter-Church School, up to 30
  • Trumpington Community College, up to 30
  • North Cambridge Academy, up to 5

Each has agreed to the increase “if required”. The letter says the place planning team will keep talking to schools and trusts through the autumn term, so the figure may rise.

The number has already moved once. An earlier council question-and-answer document put the confirmed total at 65 extra places, from Netherhall, St Bede’s and North Cambridge Academy. Trumpington’s 30 were added by the time the July letter went out.

Year 7 demand against places in north west Cambridge, September 2027 Two bars. Chesterton Community College, North Cambridge Academy and Impington Village College provide 570 Year 7 places between them. Cambridgeshire County Council forecasts about 700 children seeking a Year 7 place in those catchments in September 2027, a gap of about 130. Four city schools have agreed to over-admit by at least 95 places in total: Netherhall 30, St Bede's 30, Trumpington 30 and North Cambridge Academy 5. About 700 children, 570 places: the 2027 Year 7 gap Forecast demand against published capacity at Chesterton Community College, North Cambridge Academy and Impington Village College. Year 7 places at the three schools Children forecast to need a place, Sept 2027 570 about 700 Extra Year 7 places agreed for September 2027: at least 95 The Netherhall School St Bede's Inter-Church Trumpington Comm. College North Cambridge Academy 30 30 30 5 Source: Cambridgeshire County Council, letter to Year 5 parents, 1 July 2026, and its North West Cambridge questions and answers. Graphic by Cam News.
Each school has agreed to its figure "if required". The council says more places may follow in the autumn term.

Over-admission is not new here

The council’s own figures show every city secondary has been asked to squeeze in extra Year 7 pupils in at least one of the last four years. The totals:

  • September 2023: 112 extra places. Chesterton 30, Parkside 37, Netherhall 30, St Bede’s 11, Trumpington 4
  • September 2024: 91. Coleridge 40, Netherhall 30, St Bede’s 11, Chesterton 10
  • September 2025: 96. Netherhall 30, Trumpington 30, Chesterton 21, St Bede’s 6, North Cambridge Academy 5, Impington 4
  • September 2026: 63. Netherhall 30, St Bede’s 10, Trumpington 8, Coleridge 8, North Cambridge Academy 5, Chesterton 2

So 2027 would be the fifth year running. What has changed is that the school built to end the squeeze is now more than eight years behind.

Darwin Green Academy: eight years late and no planning permission

Darwin Green Academy was originally planned to open in September 2020. It still does not have planning permission.

The council’s project timetable, given to the North West and West Community Forum on 26 February 2026, targets planning approval in January 2027, a start on site in April 2027 and completion in November 2028. The team is discussing a partial handover so that some of the building could be used from September 2028. Total budget is about £36 million, from Section 106 contributions, council funding and the Department for Education. Morgan Sindall is the contractor and Meridian Trust will run the school.

The council’s own reason for the delay is blunt: the school sits on the Darwin Green 2/3 land, and that development has moved more slowly than expected. With 450 homes now occupied on Darwin Green 1, the council can call for the school site under the Section 106 agreement, but only once the school scheme has planning approval.

The February forum was also told what still stands between the drawings and a building site. The developer does not yet own the site. An overhead power line has to come down and go underground. The ground needs levelling with imported material, and stabilising will take “a significant amount of time”. Access and a haul road have to be agreed, drainage connections established, and archaeology trenching carried out. There is a badger sett on the site.

When it does open, the school is designed for 600 pupils, with a further phase drawn up for another 300. It is expected to start with 90 to 120 children in Year 7 only, then add a year group each September.

What it means for you

If your child was born between 1 September 2015 and 31 August 2016 and you live in Cambridgeshire, you must apply for a Year 7 place for September 2027.

  • Applications open Thursday 11 September 2026 on the council’s parent portal.
  • The national closing date is midnight on 31 October 2026. Apply after that and your child will not get an offer on National Offer Day.
  • Offers land on 1 March 2027.
  • You can change your preferences as often as you like up to the closing date, but not after it.

Two practical points follow from the over-admission decision. First, nothing about how places are allocated changes: every school still applies its published oversubscription criteria, so catchment, feeder school and siblings decide who gets in. The extra places are added to the intake, not handed out separately.

Second, list real preferences rather than one. Children living on the current phases of Darwin Green are in the Mayfield Primary School catchment, which is a feeder for Chesterton Community College. Eddington is in the Impington Village College catchment, with the University of Cambridge Primary School as a feeder. Neither is a guarantee of a place in an oversubscribed year.

Open evenings for the September 2027 intake, from the council’s published list:

School Open evening
Parkside Community College Thursday 8 October
Trumpington Community College Thursday 8 October
North Cambridge Academy Tuesday 13 October
St Bede’s Inter-Church School Wednesday 14 October
Coleridge Community College Thursday 15 October
The Netherhall School Thursday 15 October
Impington Village College Tuesday 20 October
Chesterton Community College To be confirmed

Chesterton is the catchment school for Darwin Green and is the one date the council has not been given. If you are relying on it, ring the school rather than wait.

Questions about places go to the council’s place planning team at placeplanningreferrals0-19@cambridgeshire.gov.uk.

What is being built across the city, including the housing that drives these forecasts, is on Cambridge planning.