Cabinet backed sending the Greater Cambridge Local Plan for examination unchanged on 17 November. Full Council votes on 26 November, after 2,863 comments.
The plan that decides where more than 50,000 new homes go in and around Cambridge up to 2045 is going to councillors for a final decision. Council officers say it should be sent to the government for examination exactly as it stands.
The summer consultation drew 2,863 comments from 778 people and organisations. Having read them, officers have concluded that none of them makes the plan unsound. Their report to the city council’s Cabinet recommends no changes.
When the decisions are made
Updated 18 November: Cambridge City Council’s Cabinet unanimously resolved on 17 November to recommend that Full Council submits the plan for examination, unchanged. The decision is subject to call-in, and Full Council has the final say on 26 November.
The Greater Cambridge Local Plan is a joint plan, so both councils have to agree. The city council’s announcement sets out three meetings:
- Tuesday 17 November, 5.30pm: Cambridge City Council’s Cabinet, meeting with South Cambridgeshire’s cabinet members at South Cambridgeshire Hall in Cambourne. It unanimously recommended submission, and the meeting was filmed.
- Thursday 26 November: Cambridge City Council’s full council decides whether to submit the plan.
- Tuesday 8 December: South Cambridgeshire District Council’s full council makes the same decision.
If both say yes, a planning inspector will examine the plan. The councils expect that to start in the first half of 2027.
What people objected to
Most comments were on the overall development strategy and on three big sites: the Cambridge Biomedical Campus, Cambourne North, and Grange Farm, next to the A11 and A1307. Within the city, the report lists objections and requests including:
- Cambridge Biomedical Campus: some respondents said the case for releasing Green Belt land for the campus to grow had not been made.
- North East Cambridge: objections to the area being turned into a policy framework, worries about traffic and parking, and concern about the effect on heritage and views. Anglian Water confirmed it intends to invest in the existing sewage works there.
- Abbey Stadium: Cambridge United asked for the plan to acknowledge that the club might move.
- Mill Road: calls for wider pavements, and one comment saying the bus gate should be removed.
- Water: concerns that there is not enough certainty of water supply, and that the plan relies on major water projects that could be delayed.
Other comments pulled the other way. They argued that the plan’s growth assumptions are too cautious and that it does not identify enough land to meet housing need.
What officers say
The report answers each group of comments and concludes that the plan is sound. On housing, it says the figure follows the government’s standard method, and that the plan’s sites could carry a further 24,000 homes beyond 2045. On water, it says growth has been timed to match expected supply, worked out with the Water Scarcity Group. The Mill Road bus gate, it says, is a matter outside the plan.
Officers also warn councillors off the alternatives. Rewriting policies or adding and removing sites now would need another round of consultation. That would miss the government’s deadline for plans written under the current system to be submitted by the end of 2026. The report notes that the government has since offered a three-month extension, but says planning advisers still recommend submitting as soon as possible.
What it means for you
The time for new comments has passed. Everything sent in during the August and September consultation goes to the inspector with the plan. The report says the inspector will hold public hearings and will weigh those comments.
The number of homes is smaller than it looks for the city. When the plan was published in July, the councils said around 37,000 of the 50,000-plus homes already have planning permission or are allocated in the current plans. What the new plan changes, and where, is set out on our Cambridge planning page.
Sources
- Cambridge City Council, Submission of Greater Cambridge Local Plan, report to Cabinet on 17 November 2026, for the 2,863 comments from 778 respondents, the main issues raised, the officers’ assessment, the 24,000 further homes, the options and the deadline.
- Cambridge City Council, Cabinet agenda, 17 November 2026, for the time and venue.