Fourteen sports clubs, youth centres, parks and allotments in Cambridge are to share £414,111 of developer money.

Cambridge City Council’s Cabinet approved the list on Monday 16 November. The decision was published on 18 November and is not subject to call-in.

The money comes from Section 106 agreements. These are legal deals in which developers pay towards local facilities when they get planning permission. Some of the older payments must be spent by a deadline, or the council may have to hand them back.

Overview

  • The biggest sums go to Chesterton Sports Centre (£86,532) and Parker’s Piece (£85,000).
  • Parker’s Piece gets mains power in two quarters of the green, so events can stop using generators.
  • Ten sports and community projects share £250,611. Four park and allotment projects share £163,500.
  • Officers can now hand out smaller leftover sums, up to £25,000 each, without going back to councillors.

What each project gets

The Cabinet report lists the projects and what the money is for.

Project Amount What it pays for
Chesterton Sports Centre £86,532 Sports hall floor, screens and blinds, pitch improvements and new goals
Parker’s Piece £85,000 Mains power to two quarters of the green
Coldham’s Common £65,000 Better footpath access from the Abbey Leisure Complex and to the railway footbridge
Parkside Pools £45,000 A larger display and scoreboard by the pool, added to an earlier allocation
Centre 33 £40,000 Upgrades to the young people’s charity’s Cambridge centre
Abbey Leisure Complex £35,000 More surfacing around the outdoor gym and Youth Cabin, for table tennis and fitness classes
Nightingale Pavilion £13,500 Steel railings around the pavilion
Chesterton Indoor Bowls Club £10,000 New seating, cafe tables and chairs
Darwin Green and Clay Farm allotments £10,000 Community composting bays and storage
Romsey Mill £8,291 Sports hall floor, badminton posts and nets, basketball hoops
Cambridge Dive Gym £4,680 An AirTrack and air mattress for training at Netherhall Academy
Trumpington pitches £4,608 Mobile football goals on the Academy sports field, for public use
Kings Hedges “Pulley” play area £3,500 Landscaping and a picnic bench between the splashpad and the play equipment
Abbey Leisure Complex £3,000 Extra 9v9 goals on the 3G pitch, which hirers asked for
Bar chart of 14 Section 106 allocations approved by Cambridge City Council on 16 November 2026. Chesterton Sports Centre £86,532, Parker's Piece power £85,000, Coldham's Common access £65,000, Parkside Pools scoreboard £45,000, Centre 33 £40,000, Abbey Leisure Complex surfacing £35,000, Nightingale Pavilion railings £13,500, Chesterton Indoor Bowls Club £10,000, Darwin Green and Clay Farm allotments £10,000, Romsey Mill sports hall £8,291, Cambridge Dive Gym £4,680, Trumpington pitches goals £4,608, Kings Hedges Pulley play area £3,500, Abbey 3G pitch goals £3,000.
Chart by Cambridge Local News, from the council's Cabinet report of 16 November 2026.
Share this chartFacebookWhatsAppX

The report’s summary table puts the total at £411,111. Its two subtotals, £250,611 and £163,500, add up to £414,111, which is also the sum of the 14 projects.

Parker’s Piece and Coldham’s Common

Events on Parker’s Piece currently run on temporary generators. The report says mains power to two quarters of the green will support community events and cut reliance on diesel and biodiesel generators.

The Coldham’s Common work is meant to make the common easier to reach on foot from the Abbey Leisure Complex. It also covers the approach to the footbridge over the railway.

Both schemes still depend on checks. The council has to confirm the full cost of the Parker’s Piece work and who maintains it. Coldham’s Common needs technical assessments and permissions first.

Why the money has to be spent now

The report says many of the council’s remaining general Section 106 payments must be spent or committed within the next 16 to 18 months. If they are not, the money may have to be repaid to developers.

The council has already put more than £870,000 of Section 106 money into local projects through reports between 2023 and 2025.

Each grant on the list is still subject to final checks. Officers must confirm the money is eligible under the original agreement, that enough is available, and that it can be spent before the deadline.

What it means for you

  • If you use these places: the work will happen over the coming months. The report gives no start dates. The council says it will talk to ward councillors, groups and facility operators as each project is worked up.
  • If you run a club or community group: officers can now approve smaller grants of up to £25,000 from the leftover general Section 106 money. Anything bigger goes to the relevant Cabinet member.